America First has an electric bill to explain
The House should keep the Senate provision that would make large data centers pay for the transmission upgrades they need.

Photo credit
On election night, Texas and Kansas both sent Democrats to the Senate. By early November 4, the Associated Press had called both chambers for the Democrats.
On Steve Bannon’s War Room, pollster Richard Barris argued that Republicans could win voters back with “economic populism.” About six in ten voters with household incomes below $50,000 told the AP Voter Poll they were worse off than two years earlier. If I were a Republican making Barris’s case to those voters, I’d start with a vote fifteen Democrats helped Republicans win.
On November 19 the Senate voted 62 to 33 for an energy bill backed by Trump. It would speed up permits for energy projects. The part I’d keep when the House takes it up concerns the cost of running transmission lines to a large data center.
What shows up on a household bill
Suppose a utility has enough equipment to serve a town today. A developer wants to put a server campus there, and the utility has to expand the grid to handle it. The developer could pay for every unit of electricity the servers use and the utility would still have construction costs to recover. If it spreads those costs across its customers, the family down the road can use exactly as much power as last year and owe more for it.
The Senate Energy Committee says federal policy generally limits a utility’s ability to charge for both use of the existing grid and the expansion a new customer requires. The bill would direct federal regulators to change that. A large data center would have to cover the transmission upgrades needed to serve it as well as the cost of service. A state could use the revenue to lower other customers’ rates. I wouldn’t promise anybody a cheaper December bill on the strength of a Senate vote. The House still has to act, and a state would have a choice about what to do with the money.
Photo credit
What Ohio puts in the contract
Ohio Power already has terms for the awkward stretch between a developer picking a site and the first server coming on. For a new project seeking at least 25 megawatts, the utility charges $10,000 to $100,000 to study how it would supply the power. Once the utility has a plan, the developer has 60 days to sign the agreements or lose its place.
One agreement covers the buildout. If the developer cancels before the scheduled hookup, it owes Ohio Power the full buildout cost. The same goes for a project the developer delays by more than twelve months before hookup. That’s an Ohio contract already in use.
I want local electricians to get that work. I’d want the developer’s signature before the utility orders the transformer.
Sources
- Associated Press · Congressional race calls
- AP Voter Poll · Household finances and the election
- War Room · November 13 broadcast transcript, Barris at 2:54
- Associated Press · Senate vote and the energy bill
- Senate Energy Committee · Data center transmission costs
- Ohio Power · Data center agreement and cancellation terms